Clause 62 provides that where a building not forming part of the phase 1 works authorised in the Bill—for example, a building over a station—is built to replace a building demolished or substantially demolished under the Bill, the planning application for that replacement building must be accompanied by an environmental assessment subject to certain conditions set out in subsection (1). It is a very sensible provision.