Planning and Infrastructure Bill - Committee (3rd Day) – in the House of Lords at 3:21 pm on 1 September 2025.
Baroness Taylor of Stevenage:
Moved by Baroness Taylor of Stevenage
72: Clause 16, page 22, leave out lines 12 and 13Member’s explanatory statementThis Amendment is a drafting correction which would remove the definition of “qualifying distribution agreement” from clause 16. The definition is unnecessary because the term is already defined for the purposes of clause 16 in clause 13(8).
Baroness Taylor of Stevenage
Parliamentary Under-Secretary (Housing, Communities and Local Government), Baroness in Waiting (HM Household) (Whip)
My Lords, Amendment 72 in my name seeks to leave out lines 12 and 13 on page 22 of the Bill, removing the additional definition of “qualifying distribution agreement”. It is a straightforward technical amendment. Its purpose is to tidy up the drafting of the Bill by removing a definition that is no longer required. The term “qualifying distribution agreement” is already defined in Clause 13(8), following other changes made during the passage of the Bill. The amendment will help ensure that the legislation is clear, coherent and free from unnecessary or redundant definitions. It will not alter the substance or effect of the policy but support the overall clarity and workability of the Bill.
I hope that the Committee will support this amendment. I look forward to the debate on the other amendments in this group; I will reserve comment on them until I make my winding-up remarks. I beg to move.
Lord Lansley
Conservative
My Lords, I am grateful to the Minister for being so brief and to the point and for allowing me the opportunity to explain the purpose of the other amendments in this group in my name, which are Amendments 73 to 76. Like the Minister, I look forward to hearing from the noble Earl, Lord Russell, about grid capacity in his Amendment 79. I remind the Committee of my registered interest as chair of development forums in Cambridgeshire and Oxfordshire.
My amendments relate to Clause 17, which contains a power to give Ministers the opportunity to designate strategic plans for the purposes of the connection reforms that are taking place in relation to the transmission and distribution networks. I suppose it would be helpful—not least because it will connect to what the noble Earl, Lord Russell, will raise—for me to remind the House that this process is under way. In effect, it was commenced by the Connections Action Plan under the previous Administration in November 2023. A simple way of expressing it is by saying that there was a lot of commitment to future substantial increases in generating capacity in a range of technologies, which were increasingly forming a queue to book their potential connection to the transmission or distribution networks. However, there was considerable risk related to whether those projects would be delivered on time or at all.
The volume of such commitments made it very clear that a significant proportion of them would not be viable, because there would be an excess of what was required. The numbers varied, but I think the latest figure was something like 714 gigawatts of grid capacity relative to about 500 gigawatts of demand. Instead of the old regime, which can be characterised as “first ready, first connected”—namely, those who were planning to provide capacity simply booked a place in the queue and then, when they were ready, they were given a right to be connected—the intention now is for there to be strategic planning behind the process leading to the net-zero objectives in 2030, which were published under the Government’s Clean Power 2030 Action Plan last December.
Since then, Ofgem and the National Energy System Operator have been working on this. For the avoidance of doubt, references in Clause 17 to the independent system operator and planner, ISOP, are actually to the National Energy System Operator, or NESO. Ofgem agreed on its methodologies, I think in April, and has now, after consultation, approved the processes. I think that we are in a position—but the Minister can correct me if there is more detail—where we are anticipating, potentially in a matter of weeks, the first allocation of commitments by Ofgem to what is known as Gate 2. As I understand it, Gate 2 means that Ofgem will say that it is committed to these projects and that they will be connected to the transmission or distribution networks when they are ready and because they are needed.
There are two differences with that approach. First, the queue will be straightforward; it will be not just “first ready, first connected” but “first ready, first needed, first connected”. Secondly, the two criteria that Ofgem will apply, in the first instance, will be that there is a clear timetable—with milestones, which, if they are not met, may cause such projects to lose their place in that queue—and that they will be connected when they are needed. There is therefore a direct relationship between the strategic planning for electricity capacity in a range of technologies and the projects that NESO agrees will be brought in to supply the grid at given times in the future.
If I understand it correctly, the present strategic objective is set out in the connections annexe to the Clean Power 2030 Action Plan. It sets out a range of technologies, and capacities that are required in those technologies, and then breaks them down by regions across the country. There is therefore a plan to which the alignment should relate. The Explanatory Notes state that the designated strategic plan according to which the National Energy System Operator should work may be, for example, the Clean Power 2030 Action Plan, so we can see the relationship with that.
The Explanatory Notes do not say this, but the Delegated Powers Committee’s memorandum from the department did: in addition, the designated plans are intended to include the strategic spatial energy plan intended to be published in 2026. That is in addition to what is in the clean power plan, which has 2030 targets and ranges for its potential capacity requirements through to 2035, and will extend that to 2050 so that there is a longer strategic alignment between the people who are making substantial investments and the commitment on the part of the grid to take that supply into the grid.
All of that is just to explain where I think we are. The question, then, is: where does Parliament fit into all this? We are giving the Government, in Clause 17, the power to designate strategic plans. In so far as there is a clean power action plan and the Government designate it, there was no parliamentary process—none that I can find—associated with the clean power action plan. It was simply published by the Government. Unless I am wrong, the strategic spatial energy plan that is intended to be published next year will have no parliamentary process associated with it. So, in so far as the National Electricity System Operator and the distribution operators are required to align with a designated strategic plan, they are aligning with something in relation to which Parliament has no role.
The regulations saying that they are designated are intended to be achieved by a negative process. I think that all that Parliament will see in due course is an order made by Ministers saying that the clean power action plan and, in due course, the SSEP are designated strategic plans for the purposes of what will then be Section 17 of the Planning and Infrastructure Act. This will cut across the existing arrangements because Ofgem and ISOP or NESO, as it is variously described in legislation, must have regard to the strategy and priorities statements that are published by the Government. So the strategy and policy statement that the Government publish from time to time—the last time was in the earliest part of 2024—is a statutory basis for the priorities that are set for Ofgem and NESO.
The first question to the Minister—and the purpose of these amendments, which are to probe how this is going to work—is: what is the relationship between the present strategy and policy statement, as published by the previous Government, and the designated strategic plans? Clearly, it would be right—necessary, in my view—for the present Government to publish their own strategy and policy statement to give effect to their intentions under the 2030 action plan and, in due course, the spatial energy plan.
The second question is: is it the Government’s intention to publish next year, in line with the strategic spatial energy plan, a new strategy and policy statement?
The third question is: why is the strategy and policy statement not the right and sufficient means by which the Government set out the strategic priorities for Ofgem and NESO? I ask this because Section 165 of the Energy Act, which requires them to have regard to these statements, makes clear that the strategy and policy statement is the one that is published under Section 131(1) of the Energy Act 2013 and that it can be published only if the procedural and consultation requirements in Section 135 of the 2013 Act have been complied with. It will not surprise noble Lords to know that this means that it should be published in draft; that it should be the subject of consultation; and that it should then be laid before Parliament and subject to the approval of both Houses prior to its designation as a strategy and policy statement.
That being the case, the intention of my amendments is to substitute that statement and ask, “Why shouldn’t the Government use that?” The difference is that this would have to be consulted on and approved by both Houses of Parliament before it were the designated plan for the purposes of Ofgem and NESO. When the time comes, I would be grateful for the Minister’s answers to some of those questions; obviously, I reserve the right to come back to this on Report.
Earl Russell
Liberal Democrat Lords Spokesperson (Energy and Climate Change)
3:30,
1 September 2025
My Lords, I remind the Committee of my recorded register of interests: I am a non-executive director and a board member of the Water Retail Company. I will speak to my Amendment 79 and respond to the amendments on connections reform.
Amendment 79 calls on the Government to insert a new Clause into the Planning and Infrastructure Bill under the heading of “increasing grid capacity” and proposes that, within three months of the Bill becoming law, the Secretary of State should publish a plan to achieve two simple yet crucial objectives: to reduce the cost and the time taken for new connections to the electrical transmission or distribution system; and to permit the development of local energy grids. The need for this amendment should be beyond reasonable doubt. I am concerned that, if these reforms are not made, we will not be capable of meeting the Government’s stated objective, which we share, to achieve clean power by 2030—a key step on our overall climate change and energy targets.
To decarbonise, we must electrify. Electricity demand is set to rise by at least 11% before 2030 and at least double by 2050. How we heat our homes, how we travel and how we power our industry must all be by electricity, which demands wiring everything up and ensuring that both low-voltage and high-voltage networks are fit for purpose. I would argue that this is one of the biggest societal energy changes since the Industrial Revolution and is only some five years away, which is merely the blink of an eye in planning terms. At present, the delay in getting grid connections is one of the greatest obstacles to decarbonisation, to developing new housing and industry, and to increasing our economic output as a country. Our businesses and communities are waiting seven to 10 years—even longer in some cases—before they can secure the right to feed clean energy into the system or to make power connections. Developers in grid hotspots—or “not spots”, potentially—are reporting connection waits of several years as being typical.
We need to be prepared and to get this stuff done. My amendment is designed to help do that. If we are going to be a leader in renewable energy and to get all the renewable energy in place, the grid connection system needs to be reformed. I very much recognise the Government’s recent reforms to try to update the grid connection system. In April 2025, working alongside Ofgem and the National Energy System Operator—NESO—the Government announced reforms to prioritise clean energy and infrastructure for grid access, aiming to eliminate so-called zombie or speculative projects and to fast-track the shovel-ready schemes that are set to go. The new target model option, TMO4+, introduces stricter queue management, milestone targets and progressive penalties for lagging projects, as well as prioritising the projects that are crucial for clean power and our overall economic growth.
These reforms are intended to help deliver that 2030 clean power plan, unlocking up to £15 billion in investment and supporting a more responsive and modern grid system. These are all steps in the right direction, and we definitely welcome how the Government have made progress since they came to power, but I feel that more needs to be done, hence the amendment that I put forward here. I worry that, if we do not do more, we will simply not be ready and will not hit these targets.
The second element of my amendment touches on local energy grids. Local energy grids are still in their infancy, but my party very much supports them. They empower our local communities and help them to benefit from the clean power revolution that is coming. Their efforts are quiet, modest and determined, and I want this Government to do more to support them. I believe they are essential in galvanising public support and helping the Government to take communities with them on this journey. Alongside many others across both Houses of Parliament, I fought to get community energy into the Great British Energy Act and I am delighted to have done that.
However, more help is needed to get this stuff over the line. Local energy grids are important and will benefit the country. They help to make the grid more secure and resilient. They reduce the need for transmission and the loss of transmission time, and they reduce the need to invest in the high-voltage grid overall. They take our communities with us and bring support. We all need that: this Government need that and we need that. Our communities should benefit from the revolution that is taking place. My amendment is designed to help and to support the Government. My hope is that the Government can support this amendment, or it would be appreciated if they brought forward an amendment on Report.
I turn briefly to the other amendments in this group. I recognise that the Minister has put forward a drafting amendment and we are fine with that. On Amendments 73 to 76 in the name of the noble Lord, Lord Lansley, we recognise what they are about and welcome the questions that the noble Lord raises. These are important issues, which we should discuss in Committee, about the replication of policy and policy statements, and how those systems are set up and will work in practice.
However, as we go into this rapid period of change, my worry is that, if his amendments are passed, we could end up with a system that is centralised more in Westminster, is less responsive to the changes that need to happen at pace and at scale and is not as well connected to the communities and those on the ground facing change. Those would be my general concerns with those amendments, if agreed, but I look forward to the Minister’s response and I think it is important that those amendments were raised. I look forward to further debate on this group.
Baroness Neville-Rolfe
Shadow Minister (Treasury)
My Lords, connections reform is very important if we are to give the grid capacity. The noble Earl, Lord Russell, is right in wanting to speed things up and to ensure that these connections are not too costly. That matters whether you want more renewable energy in the mix or would prefer—as I would—to continue with a mixed supply, including better and continued use of North Sea oil and gas.
However, the fact is that the grid is not resilient and everything is too slow. We have too many layers of decision-making, too much strategising, too many bureaucratic rules and, therefore, not enough speed and determination. I know that that is behind the Government’s planning reforms. I fear that my noble friend Lord Lansley’s amendments could also slow things down, but he may be able to reassure me on that. I look forward to the Minister’s response on how we can ensure that these changes will speed things up and get us the reforms that we need, if the economy and the energy economy are to work well in the months and years ahead.
Baroness Coffey
Conservative
My Lords, I agree with my noble friend Lord Lansley’s approach of being specific about what it is that developers and investors should be looking at instead of what the latest designated strategy might be. This approach also makes sure that we do not end up with more reasons for judicial review, when it is left to judges to determine what is the strategy or where there is nuance and so on. My noble friend made points about making that direct link to understanding a moment in time and that the measure has been through the parliamentary aspect of the process, initiated by the Government of course. That simplicity will in fact help the Government in achieving a lot of the aims which they seek.
My noble friend Lady Neville-Rolfe is also right that we need to improve the connections. One thing that has been frustrating is that Ofgem, for what it is worth, has overinterpreted existing legislation. The previous regime was National Grid, as it was, now it is NESO. It could have had more flexibility in order to have more certainty on what was to be connected, instead of connections agreed 10 years ago, with very little, as a consequence, happening. That is partly because it leads to a whole bunch of work and fear in local communities on what further infrastructure will be used for the transmissions.
To some extent, this is where the noble Earl, Lord Russell, is trying to go with speeding up the connections, but I am concerned about two aspects of the approach that he is suggesting. I understand what he says about local energy grids, but there are significant parts of the country where the energy being generated is not intended for any use near that particular part of the country, whether it is in parts of Scotland or parts of coastal Britain. It is intended to be transmitted—I am not entirely sure where, and perhaps I need to educate myself further on Liberal Democrat policy and what exactly the local energy grids are—but I would ask on whom the costs fall.
A lot of this drives costs on to consumers. My concern is around what I have seen where energy developers have not got the CfD that they were expecting or hoping for and then have either cancelled projects or reduced the amount of energy that they are prepared to generate. That is a commercial decision, but one reasons for aspects of centralisation is that it is largely not taxpayer subsidised—well, it is taxpayers in a lot of the cases—but there is also an issue around bill payer subsidy in how we get the energy grid that we need in the future.
Where I disagree with the noble Earl, Lord Russell, is that this will always require a huge amount of centralisation in any consideration of how we get the right energy grid right around the world. It is to that end that I hope that the Minister will consider carefully the amendments tabled by my noble friend Lord Lansley, because that simple change of legislation would in fact unlock a lot of certainty and bring clarity, which is to the good of our future electricity capacity.
Baroness Bloomfield of Hinton Waldrist
Shadow Minister (Wales), Opposition Whip (Lords)
3:45,
1 September 2025
My Lords, I will speak briefly to this group of amendments, which relate to the connections reform provisions within the Bill. These are largely technical and drafting amendments, but they are none the less important to ensure clarity and alignment across the legislation. I agree with many of the issues raised by my noble friends Lady Neville-Rolfe and Lady Coffey, particularly anything that slows down the grid connections process or adds more cost to the consumer.
Let me start by welcoming Amendment 72, in the name of the noble Baroness, Lady Taylor of Stevenage, which, as she stated in her admirably brief opening, makes a simple drafting correction. It removes the definition of “qualifying distribution agreement” from Clause 16, as it is already defined in Clause 13(8). This is a helpful tidying up amendment that improves the consistency of the Bill’s language, and I am grateful to the noble Baroness for bringing it forward.
Amendments 73 to 76, tabled by my noble friend Lord Lansley, would also serve to improve the clarity and coherence of the Bill, particularly in relation to NESO and its responsibilities. Amendment 73 would ensure that NESO is required to have regard to the strategy and policy statement under Section 165 of the Energy Act 2023, rather than the designated strategic plan. This helps to bring the language of the Bill in line with existing legislation and policy frameworks.
Amendment 74 makes a similar adjustment to Clause 17, ensuring that NESO must have regard to the strategic priorities set out in the strategy and policy statement under the 2023 Act. Amendment 75 then defines “strategic priorities” as those contained in the most recent strategy and policy statement issued under that Act—again reinforcing consistency and legal precision. Amendment 76 replaces references in Clause 17 to “designated strategic plans” with “strategic priorities”, to align terminology with Section 165 of the Energy Act 2023. My noble friend Lord Lansley has put forward a strong case for these changes to the Bill, and they appear to be sensible and constructive amendments.
Finally, Amendment 79, in the name of the noble Earl, Lord Russell, raises an important issue by highlighting the delays and high costs associated with connecting to the national grid. This amendment addresses a key barrier to energy development and considers the use of local grids as a way of improving efficiency.
This has been a good, thoughtful and short debate. I look forward to hearing the Minister’s response.
Baroness Taylor of Stevenage
Parliamentary Under-Secretary (Housing, Communities and Local Government), Baroness in Waiting (HM Household) (Whip)
My Lords, it is reassuring to hear such a degree of consensus across the House that we all want to deliver the same thing from this—speeding up the connections process. I have expressed my frustration many times before in this House that it can take longer to get a grid connection than it did to build the whole of the A1(M). That is a just a nonsense and we have to move on from it.
I thank all noble Lords who have spoken in this brief debate, particularly the noble Lord, Lord Lansley, and the noble Earl, Lord Russell, for their amendments, and the noble Baronesses, Lady Neville-Rolfe and Lady Coffey, for their comments.
I am afraid I have to oppose the amendments from the noble Lord, Lord Lansley. I understand how well intentioned they are and I greatly respect his experience in these areas, but they would have significant unintended consequences for the Government’s ability to respond swiftly and effectively to the evolving needs of our energy system.
At the heart of the amendments is a proposal to require that the strategy and policy statement, also known as SPS, designated under Part 5 of the Energy Act 2013 is used for the purpose of prioritising connections to the electricity network. I recognise the helpful attempt by the noble Lord to ensure consistency and clarity with regard to the obligations of Ofgem and the National Energy System Operator, NESO. I also fully recognise the importance of parliamentary scrutiny and do not for a moment suggest that we should seek to avoid that. But we must also be honest about the practical implications of this approach.
The SPS is subject to a rigorous process that is entirely appropriate for a high-level, overarching statement of policy. But it is not designed to accommodate the pace or specificity required to support the complex and fast-moving reforms we are undertaking to unblock and accelerate electricity network connections. We are entering a period of rapid transformation. The grid must decarbonise. New technologies are emerging. Electricity demand is shifting and increasing and the connections process must evolve to keep up.
In that context, the Government must be able to designate timely targeted guidance, potentially in the form of multiple documents, tailored to different parts of the sector, such as generation or demand connections, or technology-specific plans and strategies. Indeed, the Government have already signalled their intention to designate the Clean Power 2030 Action Plan and the Industrial Strategy—both existing documents published recently—when the necessary powers are available. These are concrete, strategic documents that will help the industry to plan and invest with confidence, hopefully meeting some of the concerns of the noble Baroness, Lady Neville-Rolfe. But these amendments would prevent that. They would limit us to a single document—the SPS—and, in doing so, tie our hands at precisely the moment we need the most flexibility, creating potential delays and preventing the granular and specific strategic direction required for the grid connection process.
There is a further and more fundamental issue. Distribution network operators—DNOs—have no legal obligation to have regard to the SPS. These companies are critical to the delivery of connections reform and are responsible for connecting a significant volume of new generation and storage that will connect directly to the distribution network. They are privately owned and operated and the SPS was never intended to bind them. To attempt to do so now would be not only inappropriate but unworkable.
If we are serious about reforming the connections process—as I believe we are; we have heard that this afternoon—we must ensure that our strategic plans can apply to the full range of actors involved. That means having the ability to designate plans that are fit for purpose, timely and applicable to the right parties. The strategy and policy statement is a high-level strategic document intended to provide Ofgem and NESO with clear direction over the Government’s strategic priorities and desired outcomes for the duration of our term to inform decision-making. In contrast, as I have said, designated plans for the purpose of connections reform may include more granular, tactical guidance. These documents are designed to complement, not conflict with, the SPS.
In response to the noble Lord, Lord Lansley, I would also say that plans are in place and being implemented for the connections to the transmission and distribution system. In November 2023, as the noble Lord mentioned, the Connections Action Plan was published, setting out expectations for the scale and pace of reform. This formed the basis for the National Energy System Operator’s connection reform proposals, which Ofgem have just approved. The broad ambition, on which legislative measures have been based, will see faster electricity network connection dates offered, at both transmission and distribution.
The noble Lord asked me a very specific question around the Gate 2 process. The implementation of current connection reforms is under way, as I said. We are working closely with NESO and Ofgem, and we are anticipating the Gate 2 decisions in the coming weeks; “coming weeks” is one of those expressions that I have got used to as I have been a Minister.
The Bill as drafted is intended to ensure that we have the tools to deliver the energy transition effectively. The measure as drafted strikes the right balance. We believe that it provides a clear mechanism for designating strategic plans while preserving the flexibility —which we know we will need—to respond to a rapidly changing sector. I therefore kindly ask the noble Lord not to press his amendments.
I turn now to Amendment 79, tabled by the noble Earl, Lord Russell. He said that he believes this is the biggest change since the Industrial Revolution in terms of power accessibility. I do not disagree with that statement. Let me begin by stating that we are in full agreement that the current delays arising from the first come, first served approach to grid connections are absolutely no longer tenable; I hope I have made that very clear. For this reason, in December 2024, the Government published the Clean Power 2030 Action Plan. This document outlines our plan to work collaboratively with the National Energy System Operator—NESO—and Ofgem to deliver a fundamental overhaul of the connections process.
The objective is to accelerate connection timelines for the most critical projects and to unlock billions of pounds of investment for renewable energy generation. Through the implementation of these reforms, it is estimated that up to £5 billion in unnecessary network reinforcements could be avoided. In turn, this should lead to long-term savings for consumers through lower electricity Bills.
The reforms in question have been developed by NESO in close consultation with both industry stakeholders and Ofgem, following all requisite formal procedures, including public consultation. Ofgem has since approved these proposals and implementation is now well under way, as I have already mentioned.
This Bill is intended to support the reforms. Notably, the Bill will confer powers on the Secretary of State to designate strategic plans. These plans must be taken into account by both NESO and distribution network operators when exercising their functions in relation to grid connections.
It is anticipated that the Secretary of State will initially designate the Clean Power 2030 Action Plan and the Industrial Strategy, followed in due course by the proposed strategic spatial energy plan. These strategic documents are designed to reflect the needs of the nation’s energy system, including measures to address the inefficiencies of the current grid queue by prioritising projects of greatest national importance. Introducing a new statutory requirement for a further plan would risk delaying this progress and might introduce unwelcome uncertainty for industry participants.
On the matter of local energy grids, we do not consider that there is any regulatory impediment. The necessary infrastructure, including local networks that integrate both generation and demand, is already permissible. Such networks may be developed and operated by distribution network operators or independent network providers, or under private wire arrangements via statutory licence exemptions.
We are also firmly committed to supporting local and community energy initiatives. These play a vital role in the UK’s broader energy landscape and we are determined to ensure that communities continue to benefit directly from the transition to clean energy. We will be discussing more about that later this afternoon.
To that end, Great British Energy will work in partnership with mayoral combined authorities, community energy organisations and the devolved Administrations. This collaboration will include the provision of funding and strategic support, from planning advice to technical guidance, for local community energy stakeholders. I trust this explanation provides sufficient reassurance to noble Lords.
Lord Lansley
Conservative
4:00,
1 September 2025
I thank the Minister for that. Is it then the Government’s intention to publish a new strategy and policy statement under the Energy Act? At the moment, legislation requires Ofgem to have regard to what is effectively an out-of-date strategy.
Baroness Taylor of Stevenage
Parliamentary Under-Secretary (Housing, Communities and Local Government), Baroness in Waiting (HM Household) (Whip)
I hope I picked up that question during my response. I will just check back to make sure that I got the wording right. I think that is the case but I will confirm it to the noble Lord in writing. Still, I think he is correct in his assumption.
I trust that explanation provides a sufficient response for the noble Lord, and I ask him not to press his Amendment.
Amendment 72 agreed.
Clause 16, as amended, agreed.
Clause 17: Managing connections to the network: strategic plans etc
Amendments 73 to 76 not moved.
Clause 17 agreed.
As a bill passes through Parliament, MPs and peers may suggest amendments - or changes - which they believe will improve the quality of the legislation.
Many hundreds of amendments are proposed by members to major bills as they pass through committee stage, report stage and third reading in both Houses of Parliament.
In the end only a handful of amendments will be incorporated into any bill.
The Speaker - or the chairman in the case of standing committees - has the power to select which amendments should be debated.
As a bill passes through Parliament, MPs and peers may suggest amendments - or changes - which they believe will improve the quality of the legislation.
Many hundreds of amendments are proposed by members to major bills as they pass through committee stage, report stage and third reading in both Houses of Parliament.
In the end only a handful of amendments will be incorporated into any bill.
The Speaker - or the chairman in the case of standing committees - has the power to select which amendments should be debated.
A parliamentary bill is divided into sections called clauses.
Printed in the margin next to each clause is a brief explanatory `side-note' giving details of what the effect of the clause will be.
During the committee stage of a bill, MPs examine these clauses in detail and may introduce new clauses of their own or table amendments to the existing clauses.
When a bill becomes an Act of Parliament, clauses become known as sections.
Ministers make up the Government and almost all are members of the House of Lords or the House of Commons. There are three main types of Minister. Departmental Ministers are in charge of Government Departments. The Government is divided into different Departments which have responsibilities for different areas. For example the Treasury is in charge of Government spending. Departmental Ministers in the Cabinet are generally called 'Secretary of State' but some have special titles such as Chancellor of the Exchequer. Ministers of State and Junior Ministers assist the ministers in charge of the department. They normally have responsibility for a particular area within the department and are sometimes given a title that reflects this - for example Minister of Transport.
Secretary of State was originally the title given to the two officials who conducted the Royal Correspondence under Elizabeth I. Now it is the title held by some of the more important Government Ministers, for example the Secretary of State for Foreign Affairs.
A parliamentary bill is divided into sections called clauses.
Printed in the margin next to each clause is a brief explanatory `side-note' giving details of what the effect of the clause will be.
During the committee stage of a bill, MPs examine these clauses in detail and may introduce new clauses of their own or table amendments to the existing clauses.
When a bill becomes an Act of Parliament, clauses become known as sections.
A proposal for new legislation that is debated by Parliament.