Pace of construction of homes on NHS land (1)

Questions to the Mayor of London – answered on 17th October 2019.

Alert me about debates like this

Photo of Onkar Sahota Onkar Sahota Labour

What is the average time between planning permission being granted and construction beginning for homes on ex NHS land?

Photo of Sadiq Khan Sadiq Khan Mayor of London

The GLA does not collect this data. The Government’s Public Sector Progress Report, May 2019, shows progress on sites sold through the previous programme (2011 – 2015) and current programme (up to end of March 2018) for Department of Health and Social Care sites in London. Where data is available, this indicates the quickest time from grant of planning consent to start on site was nine months and the longest was three years and 11 months.