Energy Security and Net Zero – in the House of Commons at on 27 February 2024.
What recent discussions she has had with Cabinet colleagues on delivering new nuclear power stations.
What steps she is taking to increase nuclear energy capacity.
What steps she is taking to increase nuclear energy capacity.
What steps she is taking to increase nuclear energy capacity.
The civil nuclear road map reconfirmed the Government’s ambition to deploy up to 24 GW of nuclear power by 2050. It sets out plans to make investment decisions about 3 GW to 7 GW every five years between 2030 and 2044.
I thank the Minister for his answer. New nuclear holds the key not only to ensuring energy security but to creating thousands of high-skilled, well-paid jobs in the areas where it is located, but too often the planning process can take years, even on sites where there is long-established nuclear use. Has he discussed with ministerial colleagues what can be done to shorten that process significantly?
I can confirm that I have had those conversations, and the Government are exploring the potential for reducing regulatory burdens for the consenting and licensing of new nuclear power stations without impacting safety, security or environmental protections. We are also looking to introduce a range of other streamlining measures, including the action plan for reform, which sets out reforms to the nationally significant infrastructure projects regime.
Will the Minister confirm that Nuclear Decommissioning Authority-owned land adjacent to Sellafield will be made available for new nuclear? More specifically, will enough land be made available to accommodate two 470 MW Rolls-Royce power stations and their ancillary buildings and spaces?
I can confirm that Moorside is indeed a candidate for new nuclear, and it is one of a number of potential sites for hosting civil nuclear projects. Great British Nuclear is currently running a competitive process to select those small modular reactor technologies best able to facilitate operational projects in the 2030s. That said, the project needs to run its course, and I know my hon. Friend will understand that no decision on sites has yet been made.
The UK’s first nuclear fusion power plant is due to be built a short 45-minute drive from Lincoln. It will increase energy generation and hopefully limit the amount of agricultural land being used to house solar farms. Will my hon. Friend update the House on the role that institutions such as the University of Lincoln will have in providing research and training for these types of power plants and their associated advanced jobs of the future?
It is indeed a very exciting time for fusion in this country. Our Fusion Futures programme will provide up to £55 million over five years to train more than 2,200 people, helping meet the demands of our growing fusion sector. That will expand our existing fusion training programmes through work with universities such as the University of Lincoln, colleges and employers, and provide a pipeline of highly skilled scientists, engineers and technicians at all career levels, from apprentice to post-doctoral fellow.
Berkeley has secured incredibly exciting investment in nuclear innovation with a consortium involving Rolls-Royce and the University of Bristol. A low-carbon energy park with international status at Berkeley and Oldbury, next door, go hand in hand as the Severn Edge project. The Government have a good opportunity to meet their energy security ambitions and lead the way. Will my hon. Friend provide assurances that he will work with Western Gateway on Severn Edge? I heard him say that the competition has to run its course, but will the course be run ahead of the summer recess?
My hon. Friend is tempting me. Oldbury is a candidate for new nuclear, and one of a number of potential sites that could host civil nuclear projects. It is exciting and encouraging to see the number of sites and projects coming forward for investment. As I said, the competition has to run its course, and no decision on sites has been made, but it is very encouraging to see such interest across the country in our great nuclear future.
Nuclear power plants come with a huge up-front capital cost. Even small modular reactors have a considerable price tag, so it is important that the Government get their procurement right for once. Does the Minister agree that SMRs offer possibilities for economies of scale? A large number could be commissioned at once, giving potential savings to the taxpayer while delivering reliable baseload supply to the national grid.
Yes, of course I agree. That is one of the huge benefits, along with many others, of small modular reactors, which is why we are running our down selection programme, and supporting exports from this country to across the world so that other countries can join us on our nuclear journey, investing in small modular, advanced modular and gigawatt-scale projects over the next few years.
The delivery of nuclear power stations for Northern Ireland is something that I would welcome, but other parties in Northern Ireland might have concerns about it. The one thing that we in Northern Ireland can all agree on is that, as part of this great United Kingdom of Great Britain and Northern Ireland, we must be part of the manufacturing base and procurement process. Can the Minister confirm that the people of Northern Ireland will have that opportunity?
Not only can I confirm that, but I put on record my support to all the companies in Northern Ireland that are already integral to the supply chain for our nuclear sector. Our nuclear revival not only will deliver a more secure, robust and clean energy baseload, but has the potential to create thousands of new manufacturing and supply chain jobs across the country, and I want that to impact positively on every corner of our United Kingdom of Great Britain and Northern Ireland.
Contrary to propaganda from the Conservative side, the last Labour Government handed over a detailed nuclear development plan that ran up to 2025, with 10 sites identified for nuclear development, early discussions with nuclear developers, and a plan for a deep and secure nuclear repository. Since then, over 14 years, not one electron of new nuclear power has been produced, Hinkley C is now at risk of further delays and no progress at all has been made on the establishment of a secure storage site for nuclear waste. What assurances can the Minister give that lessons have been learned from that frankly fairly lamentable stewardship of the previous plan, and that the latest plan is set up to deliver?
I have never been accused of propagandising before. It is a matter of pride on the Conservative Benches that every single nuclear project that has ever been completed in this country has been completed under a Conservative Government—it does not look as though that is likely to change any time soon, despite the protestations and near-Damascene conversion of Labour Front Benchers on nuclear over the past few years. We are carrying on with our nuclear revival; we have set out our nuclear road map; and we are encouraging, enthusing and investing in our civil nuclear sector. I am very excited about the progress that we have made and what will take place in the sector over the next few years.