I am extremely grateful to the hon. Lady, who makes a very good point, which augments what I was saying. Housing is being built in Bedminster, for example. Where are people going to go to work? We need high-income, good-quality jobs. The businesses we have in Portishead—the spin-offs from avionics, for example—provide those kinds of jobs. The problem is: how do we get people in those areas of high unemployment and where the new housing is going to be built to where the jobs are? The danger at the moment is that not only are we unable to do that, but companies are unable to grow because of the restrictions on labour availability, they move to somewhere else and we lose the wealth from our region.
As ever, it all comes down to money. In 2017, the scheme budget was set at £116 million, assuming a line opening date of December 2021 and excluding a new requirement to fund operational costs. Following three separate Department for Transport-directed delays to the development consent order approval—one of which we debated here only last November—the pandemic, and unprecedented inflationary and market pressures, the revised forecast at completion was £210 million in December 2021. Following cost mitigations amounting to £47 million, the latest forecast sits at £163 million. After further increased regional budget contributions, that leaves a funding gap of £26.82 million, comprising £15.58 million in capital and £11.24 million in revenue, which we have requested the DFT to cover.
Just in case anyone has forgotten our debate in November, I remind them that I said then:
“A six-month delay, as suggested by the Secretary of State’s office, would have a potentially devastating impact. It is important that we understand whether this six-month figure was simply plucked out of the air and whether a shorter delay would deal with any reservations from the Department.”
That mattered a great deal to us. I also said:
“It has been assessed that the impact on cost beyond
Vol. 704, c. 653.]
I warned in November that the extra six-month delay for what I believe was an unjustified environmental assessment, or other similar delay, would put pressure on the partners in the project, who simply would not be able to find extra money of that order.
What am I asking the Minister for tonight? First, I am seeking agreement to an additional £15.58 million—that is the capital funding provision. Secondly, I am asking for agreement to implement the previously proposed governance structure, with the DFT taking on the client role. If that is not agreeable, incidentally, the funding gap increases by another £14 million. Thirdly, I am asking for agreement to work with North Somerset Council and the West of England Combined Authority to find a solution to fund the forecast additional MetroWest 1 operating subsidy cost of £11.24 million, recognising that North Somerset Council, a small unitary authority, and WECA have no funding streams for additional revenue.
The Minister recently indicated that there would be no more money in the Department, but the latest ministerial position ignores key cost drivers that have arisen in the interim period, since 2017, which are largely outside the control of the project team. Those include unbudgeted operational costs; requirements and inflationary costs, linked to associated programme delays, arising from the Department’s development consent order—that adds £28 million; DFT-led changes to the project procurement strategy, which add £6.1 million; market price increases, which are outside the control of the Government and add £39.5 million; and of course the pandemic, which adds an estimated £4.8 million.
Those numbers are tiny when we are talking about projects such as HS2. Let me remind my hon. Friend the Minister about the benefits that the project will bring that fall within the full aims of Government policy. It will significantly reduce travel time from Bristol to Portishead to 23 minutes, compared with 60 minutes-plus—on a good day—by bus and an optimistic 50 minutes-plus by car, and greatly improve people’s access to employment and services, as I outlined. It will bring more than 50,000 people in Portishead and Pill into the direct catchment area of a railway station for the first time in more than 60 years.
Regeneration of our railways has been a key aim of the Government. This project will deliver 1.2 million additional rail journeys and £7 million of revenue within 15 years of opening. It will produce benefits to the regional economy of £43 million gross value added per annum. It will remove 13 million car kilometres annually by 2041. It will bring new employment opportunities regionally and bring the benefits of economic growth to Portishead and wider North Somerset. There will be sustained environmental benefits, and the major improvement in travel to work times will bring associated personal quality of life and community benefits. What is not to like about this project?
One more push from my hon. Friend the Minister and her colleagues and we can get this project across the line. What could give our region a better boost in this time of uncertainty than to put all the worries behind us, once and for all? I look to my hon. Friend for the push.
Secretary of State was originally the title given to the two officials who conducted the Royal Correspondence under Elizabeth I. Now it is the title held by some of the more important Government Ministers, for example the Secretary of State for Foreign Affairs.
Ministers make up the Government and almost all are members of the House of Lords or the House of Commons. There are three main types of Minister. Departmental Ministers are in charge of Government Departments. The Government is divided into different Departments which have responsibilities for different areas. For example the Treasury is in charge of Government spending. Departmental Ministers in the Cabinet are generally called 'Secretary of State' but some have special titles such as Chancellor of the Exchequer. Ministers of State and Junior Ministers assist the ministers in charge of the department. They normally have responsibility for a particular area within the department and are sometimes given a title that reflects this - for example Minister of Transport.