I beg to move, That the Bill be now read the Third time.

Hon. Members will be aware that we had a very full Second Reading debate on 20 January, since when I am glad to report that considerable progress has been made. First, British Rail has reached agreement with the three remaining petitioners, and as a result the Bill was examined upstairs by an Unopposed Private Bill Committee. The Bill started in the other place. I hope very much that the House will give it a Third Reading so that it may go on to the statute book.

The House will remember that this small but very important measure provides for works on British Railways new Thames link route, which will join the rail networks of north and south London, through the City. The Bill comprises three different sets of works. The first is the realignment of the railway between Blackfriars and Farringdon, which will also involve closing Holborn Viaduct station, at the end of a short spur. There will he a new St. Paul's station on the through line. The realignment includes the creation of a shallow tunnel instead of the viaduct and bridge. Hon. Members will know that the existing bridge near Ludgate circus blocks the great prospect of St. Paul's cathedral from Ludgate circus, and indeed from the east end of Fleet street.

I am also glad to report to the House that, since Second Reading, the Corporation of London has given planning permission for the redevelopment proposals on the old Holborn Viaduct site, which will pay for these works entirely. The latest estimate of the cost for Work No. 1 of the Bill is about £46·5 million.

The second section of works involves the reinstatement of tracks and equipment in two short abandoned tunnels that are just to the north of King's Cross station, thus connecting the Thames link with the east coast main line. That part of the works will cost £3 million. British Rail believes that the cost can be justified because of the increase in passenger receipts.

The third section of works detailed in the Bill—