Doncaster By-pass

Part of Oral Answers to Questions — Roads – in the House of Commons at 12:00 am on 11th July 1956.

Alert me about debates like this

Photo of Mr Harold Watkinson Mr Harold Watkinson , Woking 12:00 am, 11th July 1956

I know the great urgency of this scheme. The preliminary survey is now done, and I am publishing tomorrow the draft scheme for fixing the line of the by-bass. I must then, as the Statute provides, allow some months for the lodging and consideration of objections. As soon as the line is fixed, the process of land acquisition can start, and at the same time the detailed engineering plans be worked out. The time taken to acquire the land depends largely on the number of objections.

All this preparatory work on this major by-bass, with its 15 miles of dual carriageways costing some £5 million, is being pressed forward as fast as possible. No construction work can start until it is finished and the contracts let. The only expenditure in 1956–57 can therefore be on preparatory work. £4,000 has already been spent on this.