To ask the Secretary of State for Energy and Climate Change what the Nuclear Decommissioning Authority's latest estimate is for the total cost of decommissioning the Sellafield plant.
The Nuclear Decommissioning Authority's latest estimate of the total lifetime cost of decommissioning the Sellafield site is £36.6 billion (discounted) as set out in its annual report and accounts for 2011-12.