To ask the Minister of State, Department for Transport how much the improvements to the Black Cat roundabout at the A1/A421 junction at Eaton Socon cost; and for how long the improvement works affected traffic on the A1.

Photo of Chris Mole

Chris Mole (Parliamentary Under-Secretary, Department for Transport; Ipswich, Labour)

Improvements to the Black Cat Roundabout at the A1/A421 Junction at Eaton Socon were carried out as part of the A421 Great Barford Bypass project and as such were not costed separately.

Traffic management and speed restrictions were instigated at the Black Cat Roundabout in June 2005 while work took place to enlarge the roundabout. The work took approximately 14 months to complete.