Due to changes made to the official Scottish Parliament website at the start of 2011, our parser that used to fetch their web pages and convert them into more structured information has stopped working. We’re afraid we cannot give a timescale as to when we will be able to cover the Scottish Parliament again. Sorry for any inconvenience caused.

Photo of John Farquhar Munro

John Farquhar Munro (Liberal Democrat) | Question S3W-39646

To ask the Scottish Executive what further steps are needed for the reopening of Conon Bridge railway station; how the reopening process will be managed, and what the timescale is.

Photo of Keith Brown

Keith Brown (Scottish National Party)

The steps required to be undertaken to enable Conon Bridge Station to be re-opened are:

Network Rail ProcessTimescales
Detailed Design WorkUp to 6 months
Procurement StageAt least 6 to 9 months
Construction and CommissionUp to 12 months

It is anticipated (subject to funding being made available) that Network Rail would take over the scheme as project manager to enable the procurement and construction work to take place.