Tom Harris (Parliamentary Under-Secretary, Department for Transport; Glasgow South, Labour)

The clause allows the Secretary of State, by means of an order, to disapply the deemed planning permission granted by clause 10(1) in respect of maintaining or altering any Crossrail work from the date specified in the order. That is most likely to be used in the case of the electrification and signalling work done on sections of the existing railway network. It will ensure that a single planning regime covers works in relation to existing track after the Crossrail construction phase has been completed. In the event of a disapplication, any such development would be subject to the normal provisions of the Town and Country Planning (General Permitted Development) Order 1995 applying to development authorised by a local Act.